Cardinal Point FY2025 Review
Scope
Reviewed financial statements for Cardinal Point Builders (S-corp, residential construction) for the year ended 12/31/2025. Required annually by Fifth Third under the $2M line of credit — bank deadline May 31. Marcus Webb leads with Tom Kowalski on analytics support; performed under SOP Review Engagement Checklist including the construction WIP addendum.
Objective
Issue review report in time for the LOC renewal; get the percentage-of-completion WIP schedule tight enough that the bank stops asking questions. Last year's issuance ran to May 29 and the lender noticed.
Timeline
- 1/12/2026 — Independence confirmation and engagement letter signed (SafeSend)
- 3/23/2026 — PBC list out via Liscio; deliberately post-3/15 so their bookkeeper could close the year
- 4/14/2026 — Trial balance received; WIP schedule received 4/20 after one SOP PBC Request Process escalation
- 4/27–5/1/2026 — Fieldwork: analytics, WIP job-by-job review (14 open jobs), inquiry of owner and PM
- 5/6/2026 — Found it: the Hilliard spec house (Job 2417) was carried at 78% complete but cost-to-cost math said 61% — $94K of gross profit pulled forward. Client agreed to the adjustment without a fight.
- 5/18/2026 — Rep letter signed
- 5/22/2026 — Report issued. WIP note expanded this year: added contract asset/liability rollforward and remaining-performance detail
- 6/3/2026 — Fifth Third relationship manager confirmed receipt; LOC renewed at $2M, same pricing. Bank satisfied.
Status as of 7/13/2026
Closed and issued. File wrapped and archived 6/10. The 1120-S (also ours, extended) picks up the adjusted numbers — on the 2025 Extension Season board for September.
Budget vs. actual
Budgeted 85 hours; came in at 91. The overage was entirely Job 2417 — recomputing estimated costs at completion with the PM took two extra sessions. Fee held at the fixed $31K bundle per SOP Billing and Collections; Marcus noted we should scope a WIP-schedule tune-up as a separate fall advisory project rather than eating it inside the review again.
Open items / next steps
- 1120-S prep (Tom) targeted for early September; Diane signs
- Marcus to pitch a quarterly WIP review ($1,200/qtr) at the fall planning meeting — three straight years of estimate drift says they need it
- Calendar the FY2026 review kickoff for early January; bank deadline stays 5/31/2027